Envi Con Engineering GmbH

Navigation
Lichterfelde

Reference: CC-CHP Lichterfelde

Gas and Steam Power Plant

Characteristic Data:

Power output: approx. 300 MWel
Thermal output: approx. 120 MWth
Fuel: natural gas

Type of cooling:

  • circulating cooling system via natural draft cooling tower

Trial run:

  • expected ending 2016

Description of site:

Berlin Lichterfelde, Germany

Site characteristic:

  • central site in the south of Berlin
  • former combined heat and power station which is in operation since more than 30 years will be extended by a combined gas and steam power plant and two additional hot water boilers in order to ensure the heat and power supply in the south of Berlin

Particularities/constraints:

  • Integration of the new plants in an already existing power plant area. Due to the central location and the accompanied lack of space the power plant location poses a challenge
  • The combined cycle power plant and the hot water boilers were awarded as separate lots

Project description:

  • new construction with integration in already existing power plant location
  • usage / development of existing infrastructure

Scope of services:

  • Architectural engineering
  • Completion of approval documents for change permit
  • Civil and structural engineering
  • Conceptual, basic and detail engineering
  • Piping planning
  • Detail planning of the water steam cycle
  • Detail planning of the gas supply
  • Layout planning
  • Planning in Smart Plant 3D
  • Construction supervision

Kontakt

###CONTACTBUTTONTITLE###

Rainer Teichgräber

Rainer Teichgräber

Sales Director

Phone: +49 911 48089-143
Fax: +49 911 48089-129

Customer

Iberdrola Ingenieria y Construction
Ribera de Axpe 5
48950 Eradino (Vizcaya)
Spain

Construction period

2013 to 2016

Main Service

- Completion of approval documents for change permit
- Architectural Engineering
- Project execution planning for Civil and Structural Engineering
- Design and Layout Engineering
- Mechanical Engineering for Piping